Baski
Status: In progress
Last update: 04 Nov 2026
Construction Update:
Construction at Baski is progressing according to the below schedule:
July: Concrete works completed
August: Roof installation completed
September/October: Drywall construction, HVAC & electrical installations, plastering and painting
November: Windows & doors installations, sanitary appliances, doors, carpentry and lighting
December: Final assembly of HVAC/electrical systems, furnishing / loose fittings, final facade and roof works followed by acceptance, documentation & start of hotel operations.
We will continue to share further updates and progress photos as construction advances.