Glacier View
Status: In progress
Last update: 5 June 2026
Construction Update:
Construction at Glacier View is progressing steadily, with the team currently completing the final installations and building mould preparations ahead of pouring the last concrete level and elevator shaft. The structure is now clearly advancing into its next major phase, with visible progress across all levels of the building. Preparations are also underway for the upcoming exterior and roofing works.
Delivery of roof trusses and structural frames, as well as windows and doors, is scheduled for June, with installation works planned to begin during July. Site activity remains ongoing across both structural and technical areas as the building continues to take shape.
We will continue to share further updates and progress photos as construction advances.