Nordic
Status: In progress
Last update: 15 Oct 2026
Construction Update:
Construction at Nordic is progressing according to the below schedule:
October: Construction start with concrete works
TBA: Roof installation
TBA: Drywall construction, HVAC & electrical installations, plastering and painting
TBA: Windows & doors installations, sanitary appliances, doors, carpentry and lighting
TBA: Final assembly of HVAC/electrical systems, furnishing / loose fittings, final facade and roof works
July 2027: Acceptance, documentation, handover of operations
We will continue to share further updates and progress photos as construction advances.